CBBEL performed an
engineering survey of the impact area. Potential impacts to existing
utilities were evaluated prior to utility coordination. An analysis of
the existing drainage system was performed. Proposed culvert sizing was
optimized based on hydraulic requirements and available headroom under the
existing road profile grade. The proposed crossing included pavement
widening and guardrail improvements to reduce the hazards to motorists at
an adjacent high school. Construction plan sheets and contract documents
were produced by CBBEL. In addition, CBBEL staff provided Contractor Bid
Review and comment for the project. |
|
![]() |